Minna: General Hospital extension worth N1.4bn to be completed on schedule

Date:

From Yakubu Mustapha, Minna

The delay in the completion of 134 bed capacity neo-natal General Hospital extension in Minna, Niger state has been attributed to the muddy nature of the area, discovery of 58 soakaways and four wells which stalled progress of work.

Director General, Niger state Public Private Partnership, PPP, Alhaji Shehu Kudu Mohammed gave the explanation while speaking with journalists in Minna.

He said that the developer had to excavate the land, cover all the soakaways and wells before the proper construction could commence.

Kudu however, assured that the 8 months completion period as contained in the MOU will be achieved despite the challenges.

READ MORE  Traditional rulers vow to uphold rights of girl child

He disclosed that the developer has not reached the required 36.6 percent as stipulated in the MOU to enable his agency direct the bank to release the N500 million irrevocable payment standing order IPSO and subsequent N180 million monthly release of funds.

Never miss a moment! Get the stories shaping Nigeria, delivered straight to your phone. Follow Peoplesdaily Newspaper on WhatsApp for breaking news, exclusive reports, and the headlines everyone will be talking about, before anyone else.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

Popular

More like this
Related

Tinubu’s Campaign Strategy and the Unnecessary Political Storm

By Tunde Rahman The inauguration of President Bola Ahmed Tinubu's...

VP Shettima Silences Critics With President Tinubu’s Mega North Dev’t Projects

*Outlines massive multibillion naira interventions by NEDC to address...

Minister Matawalle hails military medical university’s JAMB listing

The Minister of State for Defence, Bello Matawalle, has...

One injurd as building under construction collapses in Abuja

Panic gripped residents of the Federal Capital Territory...