By Etuka Sunday 

The Transmission Company of Nigeria (TCN) is set to commence the final stage of the construction of its new  Kaduna – Jos 330kV double circuit transmission line.

TCN said, it would be followed with the erection of eight triple-circuit towers at the intersection point of the new double circuit and existing single circuit 330kV transmission lines, to enable the stringing of the three 330kV lines.

It said, the line would be upgraded from “500 megawatts (MW) energy wheeling capacity to 1,500MW, which is 200 percent capacity increase. Reconstruction work willl be completed within eight days, from the 8th to 15th December 2021.

READ MORE  Twitter: Legacy verified accounts will lose blue tick in a few months

“Consequently, there will be power outage on the 132kV Zaria- Kaduna transmission line, 33kV Turunku, and part of the 33kV Jaji feeder, from 8 am to 5 pm daily for the eight days indicated, to ensure a safe working environment for the execution of the reconstruction work. On completion, the new 330kV double circuit transmission lines will increase the total capacity of the Kaduna – Jos line from 500MW to 1500MW”, it said. 

Meanwhile, TCN has made arrangements, according to the statement, to continue to supply bulk electricity to Jos Distribution load centers in Jos, through the Makurdi 330kV lines 1 and 2, to minimize the effect of the capacity upgrade and assure that the project will be completed on the 15th of December as scheduled. 

READ MORE  Financial company Aims to Extend Digital Services to 1m Kaduna Rural traders

The General Manager, Public Affairs, TCN, Ndidi Mbah in a statement said, the decision to reconstruct and upgrade the Kaduna -Jos SC transmission line was due to the fact that the line is overloaded and can no longer cope with the load profile in that axis. The completion of the new 330kV Kaduna- Jos DC transmission lines will resolve the present and anticipated increase in load demand on the line route. 

The statement said, “TCN’s use of multi-circuit towers in some locations will prevent the demolition of properties in heavily built-up areas and still achieve increased bulk transmission capacity along that line route. We will therefore dismantle and reconstruct eight (8) no existing single circuit towers into special triple-circuit towers. 

READ MORE  Probe panel accuses Emefiele of consenting to ‘unlawful $6m cash withdrawal’ from CBN vault

“We regret any inconvenience the load shedding may cause electricity customers affected by the reconstruction works on the line and note that the increase in capacity to 1500MW will positively impact voltage stability on the axis. Bulk power transmission will be restored immediately after reconstruction work is complete”, the statement said. 

LEAVE A REPLY

Please enter your comment!
Please enter your name here